Year: 2012 - 2013
Conceptual design
Cimenterie Nationale (CN) Port Extension
- Port Master Plan
- Main breakwater (Rubble mound type, L=1,020m @max -20.00m, 18m3 precast Accropodes blocks Type I armor layer)
- Main quaywall (L=100.00m @-16.00m MSL) for 60,000DWT ships berthing
- Crown walls / Reflector seawalls
- RC platform (4,500m2)
- Dredging of (43,800m2) @-10.00m for 10,000DWT ships and (58,000m2) @-16.00m for 60,000DWT ships maneuvering
- Works phasing
- Drawings / BoQ