PROJECTS
Tripoli Fishing Port
LEBANON
PORTS / LIFT STRUCTURES / Middle East / Fishing Ports / Slipways /
CLIENT
LEBANESE REPUBLIC
Ministry of Public Works and Transport
Directorate General of Land and Maritime Transport
CONSULTANT
SEATEC sarl
LOCATION
LEBANON - Tripoli
34°27'14"N
35°48'55"E
Year: 2014
Design
Tripoli Fishing Port
- Master Plan
- Berthing capacity (850 boats)
- Complementary works
- Rehabilitation of the existing main breakwaters L=545m @max -4.00m MSL (Rubble mound breakwater type, rocky armor layer)
- RC retaining walls
- Quaywalls (L=85m @-2.00m MSL) / Precast concrete blocks (Gravity QW)
- Quaywalls (L=140m @-3.00m MSL) / Precast concrete blocks (Gravity QW)
- Quaywalls (L=430m @-4.00m MSL) / Precast concrete blocks (Gravity QW)
- Finger Pier (Nbr=1; L=50m @-2.00m MSL) / Precast concrete blocks
- Finger Piers (Nbr=8; L=412m @-3.00m MSL) / Precast concrete blocks
- Finger Piers (Nbr=4; L=200m @-4.00m MSL) / Precast concrete blocks
- Water Outlets for basin flushing / Precast concrete blocks
- Slipway (Boats ramp)
- Dredging works for quaywalls foundations
- Infrastructure (Electrical and water supply)
- Marine accessories (Mooring bollards, fenders)
- New reclaimed platforms (17,000m2)
- Drawings / BoQ