Year: 2017
Conceptual design
Year: 2019
Design / Surveying
Anfeh Fishing Port
- Rehabilitation of the old existing port
- Master Plan
- Berthing capacity (100 boats)
- Main Breakwater (Vertical concrete type, L=20m @max -2.00m MSL)
- Quaywalls (L=360m @-2.50m MSL) / Underwater concrete blocks (Gravity QW)
- RC and bituminous platforms (5000m2)
- Infrastructure (Electrical supply, pipes, manholes, lighting poles)
- Infrastructure (Water supply, stormwater drainage, river culvert, pumps, pipes, manholes, tanks)
- Marine accessories (Mooring bollards, fenders)
- Waste water treatment plant
- Basin dredging @-2.50m MSL
- Slipway (Boats ramp)
- 23 Fishermen rooms, 1 check point (room), 1 MPWT / DGLMT room (235m2)
- Reclaimed area (5,000m2)
- Water body (3,875m2)
- Topographic survey (29,900m2)
- Bathymetric survey (4,330m2)
- Tender Documents / Drawings / BoQ / Permitting
EIA
- Environmental Impact Assessment study (SEATEC JV SES)
Works Supervision
- Contractor : Ste. Antoine Makhlouf for Trading and Contracting sal
- Duration : 24 months